A large hydroelectric power plant, costing $25 million, will be built in Artsakh’s (Karabakh) northern Martakert region, President Arayik Harutyunyan announced in Stepanakert on August 2. 

The 17.6 megawatt power plant will be built near Getavan village, and will be launched through the Artsakh Investment Fund, in conjunction with other investors.

Harutyunyan stated that prior to the 2020 war, Artsakh was a net exporter of energy, but since the end of the war, the region has had to import to meet its energy needs because a number of power plants fell under Azerbaijani control. 

Harutyunyan added that the project will be a major step in restoring Nagorno-Karabakh’s energy independence, and will stimulate economic growth.

Follow us on Telegram Telegram

Read more

Newsletter

Subscribe to our newsletter and be the first to receive our weekly digests.

By subscribing, you agree to our .

EFCSNIFCNJTI

CivilNet content, photos, and videos may not be copied, downloaded, or republished on other platforms without proper attribution. Any partial use of CivilNet video requires prior knowledge and consent from CivilNet.

FacebookLogoInstagramLogoTiktokLogoTwitterLogoTelegramLogoYoutubeLogoMailLogo

315 Arden Ave, Suite 30, Glendale, California 91203

+1(818)749-450 [email protected]

1 Northern Avenue, Office 30, Yerevan 0010, Armenia

+374(10)500-119

CIVILNET © 2011-2026. All rights reserved.

Developed by